Sunday, April 28, 2013

FEB/MAR/APR Various work

So I did dropped a ball a bit on my updates for this project, plus there wasn't that much that was done at least by me during the winter Feb I was sick a lot and March and April my dad carried quiet bit of smaller stuff that was done but here is few recent pictures and some hours that I can account for.

I also want to add mudding was horrible and tough specially for someone that doesn't have that much experience.

Hours:
Muddying and initial stage of sanding (12 x 7 hrs = 84 hrs)
Final Sanding (4 days about 5 hrs each = 20 hrs)

On Apr 9 dry-walling around stairs and under, cutting put lights openings 5 hrs x 2
On Apr 10 muddying around the stairs and under 7 hrs x 1 + 2 hrs x 1 total 9 hrs
On Apr 11 and 12 1 x 7 hrs + 1 x 7 hrs sanding mudding of under the stairs, door fittings and framing above the doors and clean up.
 
Cost:
~ $900 (4 Sets of doors purchased, 3 sheets of drywall, 4 dimmers 2way made  for LED’s and CFLs.)

 This mask saved my life!!!