To make a quick post to keep track of the hours seems that work in January will be pretty low.
Jan 9 - Drywall - Finishing 9 hrs x 2 = 18 hrs total.
Jan 24- Finishing area under steps: 7.5 x 2 = 15 hrs total
Jan 25 - Finishing area under steps 3 hrs x 2 + 3hrs x 1= 9 hrs total
Cost for 2x4's and some 2.1's and some more tapcon screws: ~$75.
Cost for oak steps: $200
Unfortunately this is starting to drag a bit too much but now I'm out of drywall and there is still some needed probably around 1-2 sheets.